new-solar-sunset

Project Update

Introduction

A planning application was submitted to North Warwickshire Borough Council on 19 December 2024 to seek approval for Camp Farm Solar. You can view the application here: http://planning.northwarks.gov.uk/portal/servlets/ApplicationSearchServlet?PKID=131217

Feedback from public consultation

We held a public consultation on our proposals from 29 May to 30 June 2024. We’d like to thank all those who came to our consultation event or provided feedback. Since the consultation closed, we’ve looked carefully at all the feedback received.

65 responses were received, with a range of comments and suggestions for the proposals that have provided valuable insights as we finalised the design. A summary of the most common topics raised and our response to them are set out below. We’ve also provided an update on the next steps for the scheme.

Landscape and visual impacts

Comments were received regarding how the landscape and visual impacts of the scheme would be mitigated, with concerns raised regarding the scale of the fencing, light pollution, glint and glare impacts, and potential loss of the natural beauty of the site.

We have updated our proposals to add an additional 1.8km of hedgerow and trees within the site to break up the solar panels and removed solar panels from the northeastern field closest to the residential properties of Hurley, to reduce potential visual impacts. We have also produced a Landscape and Visual Appraisal to assess the potential visual impacts to the surrounding areas, and a Glint and Glare assessment has been produced to consider the impacts of glint and glare from the panels, metal framework and mounts within a 1km radius of the site, and further afield for aviation receptors. Both assessments have been submitted alongside our planning application.

The Glint and Glare assessment identified that mitigation is required in some areas. This will include native hedgerows being planted and maintained at a height of at least 3.5m along the southwest, southeast and eastern boundary of the site to negate the glint and glare impacts.

The Landscape and Visual appraisal identified that while there will be significant impacts in two specific areas during construction and the first year of operation, these impacts will then reduce over time due to the planting of trees and hedges that we’re proposing, which will also be retained following decommissioning.

Wildlife and habitat protection

We received a number of comments requesting information about how wildlife would be protected and raising concerns about the potential impacts on habitats and areas of nature on the site.

We are proposing to plant wildflowers across the site and have updated our plans to add an additional 12 hectares of areas for habitat enhancement within the site. We have also completed an Ecological Impact Assessment, and a Preliminary Ecological Appraisal, which have indicated that no negative impacts on wildlife are anticipated from the proposals. These assessments have also been submitted alongside our planning application.

Public Right of Way (PRoW)

Feedback received included both support for the PRoW diversion, and concern regarding the safety of the new PRoW, with requests to add exit points along its length, for it to have a suitable surface, and not feel too enclosed. Concerns were also raised that the diversion would be disruptive to those walking between Hurley and Kingsbury.

We have now further developed our proposals for the PRoW, ensuring it has a 10m width and will be appropriately maintained and signposted. We have proposed a parallel off-road informal cycle track surfaced with an aggregate 3m wide, such as ‘crusher run’. We will also make sure the hedgerow and tree planting is maintained to ensure sight lines along the PRoW, and an exit point from the PRoW will be available at the main site access. The re-routed PRoW will be made available in advance of the existing route being closed to minimise disruption.

The cycle track will only run the length of our site, and at this moment in time will end at the Kingsbury Rifle Range boundary.  Proposals to extend the track onwards to Kingsbury will depend upon future funding (such as use of the project’s Community Benefit Fund) and agreements with relevant landowners being made.

Alternative sites and size

Comments were received expressing concern for the scale of the proposed site, alongside suggestions for alternative proposals and sites, which included suggestions that brownfield land should be used and that panels should be placed on rooftops of warehouses instead.

We have carried out a detailed four stage site selection process, and considered the alternative suggestions provided during the consultation, however, our chosen site is the only one in the vicinity to meet the requirements for a solar farm at the scale required to be viable. Regarding fitting panels to nearby buildings and warehouses – this would likely not produce the same amount of electricity as our proposals, due to the inefficiencies and difficulty to link together a network of small generators. Although the site is located on the greenbelt, we believe it is still appropriate for development, as it meets the criteria for the ‘very special circumstances’ that the government has set out for development on the greenbelt, which includes the wider environmental benefits associated with increased production of energy from renewable sources.

Community benefits

We received many helpful suggestions of how we can positively impact and contribute to the local community. We will be setting up a Community Benefit Fund, and these suggestions will be considered further should the scheme receive planning permission.

Design updates

Following the public consultation and feedback received, we made the following changes to our proposals:

  • Removal of solar panels from the northeastern field closest to residential properties, providing further space for wildlife habitat enhancement and reduction of potential landscape and visual impacts
  • Over 12 additional hectares of areas for habitat enhancement
  • An additional 1.8 kilometres of hedgerow and trees within the site to break up the areas of solar panels and add more open space to the site, reducing visual and landscape impacts
  • Revisions to the BESS and substation layout

Next Steps

A planning application was submitted to North Warwickshire Borough Council on 19 December 2024 to seek approval for Camp Farm Solar. You can view the application here: http://planning.northwarks.gov.uk/portal/servlets/ApplicationSearchServlet?PKID=131217

North Warwickshire Borough Council will then host a statutory consultation, where you will be able to comment further on the proposals directly to the council. The council will then consider any feedback received alongside the planning application to determine whether to approve or refuse it. If approved, we would look to begin construction in 2030 and expect this will take 16 to 24 weeks.